Kitchen Remodel Timeline: How Long Does It Really Take in the Twin Cities?

A realistic week-by-week kitchen remodel timeline for Minneapolis homeowners: design (2–4 weeks), permits (1–3 weeks), cabinets (6–10 weeks), and construction (4–10 weeks).

·6 min read·Minneapolis Kitchen & Bath team

The honest answer to "how long does a kitchen remodel take?" in the Twin Cities is: 3–6 months from contract to cooking in your new kitchen. The on-site construction window is shorter — typically 6–12 weeks — but the design, materials, and permit phases consume the rest of the calendar.

Here's a realistic week-by-week timeline for a typical Minneapolis kitchen remodel in 2026.

Weeks 1–2: Initial Consultation & Scope

What happens: In-home consultation, measurements, scope discussion, rough budget alignment. Most reputable Twin Cities contractors will book consultations 1–3 weeks out.

What you should be doing: Pinterest/Houzz boards, kitchen visits at showrooms, deciding on layout intent (keep walls, open up, full reconfigure).

Weeks 2–4: Design & Quote

What happens: Contractor produces 2D plans (and 3D renderings for higher-end projects), finish samples, and a detailed itemized fixed-price quote. Allow 1–2 rounds of revisions.

What you should be doing: Cabinet door style and finish, hardware, countertop material, appliance package, faucet, backsplash, flooring. Decision fatigue is real — keep moving.

Weeks 4–5: Contract & Material Orders

What happens: Signed contract, deposit paid, cabinets ordered (the longest-lead-time item), appliances ordered, flooring ordered, tile selected and ordered. Permit applications submitted to the city.

Why this matters:Material delays are the #1 cause of timeline slippage. Order everything within a week of contract signing — don't wait on tile or fixture decisions to start cabinet fabrication.

Weeks 5–14: Lead Time (No On-Site Work)

This is the quiet phase. Materials are being fabricated and shipped. Permits are being approved. Realistic lead times in 2026:

  • Semi-custom cabinets: 4–6 weeks
  • Full custom cabinets: 6–10 weeks
  • Appliances: 1–8 weeks (Sub-Zero and Wolf can be longer; check with the dealer)
  • Tile: 1–3 weeks (longer for imported zellige or specialty)
  • Permits (Minneapolis, Saint Paul, Edina, Bloomington): 1–3 weeks

For more on permits specifically, see our Twin Cities remodel permits guide.

Week 1 of Construction: Demo & Disposal

Cabinets, counters, appliances, flooring — all out. 1–3 days for a typical kitchen. We dispose of everything responsibly (Habitat for Humanity ReStore for usable items where possible).

Weeks 2–3: Rough-In

Plumbing rough-in (sink relocation, gas line, dishwasher), electrical rough-in (new outlets per code, GFCI, island circuits, under-cabinet lighting wiring), HVAC adjustments. Inspections after rough-in before drywall.

Weeks 3–4: Drywall, Paint, Flooring

Drywall patching after rough-in inspections pass. Prime and paint ceiling and walls. Install flooring (if continuous with the rest of the house, this might happen later).

Weeks 4–6: Cabinet Install

Cabinets go in once flooring and paint are complete. 1–3 days of installation for a typical kitchen. Once cabinets are set, countertop templating happens — and the counters arrive 10–14 days after templating.

Weeks 6–8: Counters, Backsplash, Appliances

Countertop install (half-day). Tile backsplash (2–4 days). Appliance delivery and install (1 day plus gas/plumbing/electrical hookups). Plumbing and electrical finish work (sink, faucet, lights, switches, outlets).

Weeks 8–10: Punch List & Final Inspection

The last 10% takes 20% of the time. Touch-up paint, hardware install, adjustments to cabinet doors and drawers, final inspections (electric, plumbing, building), final cleaning. Then a walk-through with you, warranty paperwork, and care instructions.

Common Delays — And How to Avoid Them

  • Cabinet damage in transit: 1–4 week delay. Order cabinets first thing and unpack on delivery so a replacement can be requested early.
  • Permit rejections: 1–3 week delay. Use a contractor who pulls permits regularly in your city — they know what reviewers want.
  • Discovered conditions: 1–2 week delay. Knob-and-tube wiring, galvanized plumbing, asbestos floor tile, hidden water damage. Add 10–15% contingency for any pre-1950 home.
  • Decision delays from homeowner: 1–4 week delay. Make finish decisions before demo, not during. Keep a shared decision tracker with your contractor.

How to Speed It Up

  • Start design 2–3 months before you want construction to start
  • Order cabinets the day you sign the contract
  • Pick semi-custom over full custom (saves 2–4 weeks)
  • Don't change the layout (saves permit time and rough-in time)
  • Avoid the most popular finishes (white shaker cabinets are often back-ordered)

For more on the budget side, see our Minneapolis kitchen remodel cost guide. Ready to start? Get a free quote.

Get a Free Quote for Your Project

Serving Minneapolis, St. Paul, Edina, Minnetonka, Eden Prairie & the entire Twin Cities metro. Most quotes delivered within 48 hours.

Request a Free Quote →

Ready to start your remodel?

Free in-home consultation. Detailed fixed-price quotes.

Get a Free Quote